House Update - Windows are going in!

I have lost track of which week we're in as there hasn't been much to report over the past several weeks. As for the interior, the electrical, plumbing, and HVAC are all installed. This week the security/data guys will install the security, data, video, and audio. After that we will be ready for insulation and then sheetrock.

On Saturday the windows arrived and the workers installed nearly all of them. Below are a few pics of the progress. Windows make a HUGE difference!



Front of house.



Right side of house.



Rear of house.



This is the great room. The window company got the upper center window wrong so we will be delayed a couple of weeks while the make the correct window. (Building a house is SOOO fulfilling!)



Master bath. This is one of Laura's "special windows" with the curve that she is very excited about.



The basement - aka, future "man land".